- The Utah Journeyman Electrician written exam requires 75% on 100 questions, so you need at least 75 correct answers.
- Since August 1, 2025, new candidates take one combined Theory and Code written exam plus a separate practical.
- The practical has six tasks; every task must be passed, and passed tasks are kept if you retest.
- Grounding & Bonding carries the most written questions, with ten items.
The Passing Score at a Glance
If you are searching for the UT-JE passing score, the headline number is simple: 75% on the written examination. That standard applies to the Utah Journeyman Electrician written exam administered by Prov, Inc. for the Utah Division of Professional Licensing (DOPL). The exam contains 100 questions, runs 240 minutes, is computer-based, and is open book.
But a single percentage hides a lot of what candidates actually need to know. Utah's journeyman path is not one test. It is a written examination and an in-person practical, and each has its own way of deciding who passes. This article breaks down exactly what is required on each part, how the written questions are distributed across subject areas, and what happens if you fall short.
| Component | Format | Pass Standard |
|---|---|---|
| Combined Theory and Code written exam | 100 questions, 240 minutes, computer-based, open book | 75% (at least 75 correct) |
| Utah Electrician Practical | Six hands-on tasks, 110-minute total limit, in person | Every task must be passed; conduit bending uses point deductions, other tasks are pass/fail |
What 75% Means in Real Questions
With 100 written questions and a 75% threshold, the arithmetic is direct: you need 75 correct answers to pass, which means you can miss up to 25. That is a more forgiving margin than many people assume, but it is also less forgiving than the open-book format suggests.
A few practical consequences follow from that math:
- No single domain must be perfect. The published standard is an overall score, not a minimum in each subject heading. A weak area can be absorbed if the rest of your performance is strong.
- Blank answers cost you the same as wrong ones. Since the standard is a count of correct responses, answer every question before time expires.
- Time is rarely the binding constraint. At 240 minutes for 100 questions, you have roughly 2.4 minutes per question on average. The real risk is spending that time hunting through reference books for questions you should have recognized.
For a deeper look at how demanding the exam is overall, see our guide on how hard the UT-JE exam is. For what the data does and does not show about outcomes, see what the UT-JE pass rate data shows.
Two Examinations, Two Different Pass Standards
The most common misunderstanding about the passing score is treating the whole licensing exam as one percentage. It is not. The written exam is scored as a percentage. The practical is scored task by task.
The Written Exam: A Percentage Threshold
The written component costs $85 and is delivered either at an approved testing center or through Examroom remote delivery. Your result is judged against the 75% line, full stop.
The Practical: Pass Every Task
The practical is in person and has a total limit of 110 minutes, separate from the four-hour written timer. It consists of six separately assessed tasks:
- Torque setting
- Transformer termination
- Conduit bending
- Motor Control (commercial), using a ladder diagram
- 4-way & 3-way switch wiring
- Schematic reading & wiring
Every task must be passed. There is no averaging a strong bending score against a weak wiring result. The upside is meaningful, though: successful tasks are retained, and only failed tasks must be repeated. Candidates who fail one task do not need to redo all six.
Where the 100 Questions Come From
The bulletin publishes the combined written exam's subject headings along with official item counts. These are item counts, not percentage weights, and they add up to 100. Knowing where the questions concentrate helps you decide where a missed point is most likely to hurt.
| Written Domain | Official Item Count |
|---|---|
| Conductors & Cables | 7 |
| Current | 6 |
| Definitions & General Requirements | 6 |
| Grounding & Bonding | 10 |
| Lighting & General Use Equipment | 7 |
| Motors & Controllers | 6 |
| Overcurrent Protection | 9 |
| Power | 5 |
| Raceways & Enclosures | 7 |
| Resistance | 6 |
| Services, Feeders & Branch Circuits | 8 |
| Special Occupancies & Equipment | 6 |
| State Laws & Rules | 4 |
| Voltage | 6 |
| Voltage Drop | 7 |
Grounding & Bonding: The Biggest Single Block
With ten questions, Grounding & Bonding is the largest allocation on the written exam. Missing most of this domain would consume a large share of your 25-question error budget by itself.
- Know how to navigate the NEC's grounding and bonding material quickly, since this is an open-book exam.
- Practice distinguishing grounding concepts from bonding concepts in scenario questions.
Overcurrent Protection and Services/Feeders/Branch Circuits
Overcurrent Protection (nine items) and Services, Feeders & Branch Circuits (eight items) are the next largest blocks. Together with Grounding & Bonding, these three domains account for 27 of the 100 questions.
- Expect calculation-flavored items that reward knowing which table or section to open.
- Practice working these under time pressure, not just reading them.
State Laws & Rules: Small but Easy to Lose
At four items, State Laws & Rules is the smallest allocation. It draws on Utah's 58-1 and 58-55 licensing acts and the R156-1 and R156-55b rules. Because these are narrow, lookup-style questions, they are points you should rarely give away.
For a full walkthrough of the subject areas, including the practical tasks, read our complete guide to all 21 UT-JE content areas. The count of 21 combines the 15 written headings and the six practical tasks; it does not mean the written exam has 21 domains.
Open Book Does Not Mean Easy
The written exam is open book, and that shapes how you earn your 75 correct answers. Approved references include:
- The 2023 NEC
- Ugly's Electrical References 2023
- Utah's 58-1 and 58-55 licensing acts
- R156-1 and R156-55b rules
Highlighting and permanent tabs are permitted. The only authorized calculator is the one built into Prov's test console, so do not plan around your own handheld.
In practice, open book converts the exam into a speed-and-navigation test. Candidates who have tabbed their code book well and know where Chapter 2 grounding material, Chapter 3 wiring methods, and the relevant tables live tend to bank their 75 points without panic. Candidates who open the book to learn the material on the clock tend to run short. Our UT-JE study guide covers how to organize this preparation, and our one-page UT-JE cheat sheet is useful for last-pass review of key facts.
How the Practical Is Graded
Because the practical pass standard is not a percentage, candidates often ask what "passing" looks like there. The bulletin's published structure is limited, and it is worth being precise about what is and is not established.
What Is Established
- There are six tasks and a combined 110-minute limit.
- Every task must be passed.
- Conduit bending uses point deductions; the other tasks are pass/fail.
- Passed tasks are retained; only failed tasks are repeated.
- Candidates bring the specified tools and two five-foot pieces of half-inch EMT. Prov supplies the torque wrench.
What You Should Not Assume
The bulletin's detailed sentence describing the torque-setting task is truncated, so this article does not guess at the missing details or any scoring criterion for that task. Likewise, no numeric deduction threshold for conduit bending is stated here, because none should be invented. Check the current bulletin directly for specifics before test day.
Time management matters more here than on the written side. Six tasks inside 110 minutes means you cannot afford to linger on one. Conduit bending in particular rewards deliberate, accurate work because it is the one task graded with point deductions rather than a flat pass/fail.
Failing and Retaking: Timelines That Matter
A missed passing score is not the end of the process, but the bulletin sets waiting periods you should know about in advance.
- Normal retest wait: 30 days.
- After six failed attempts: 120 days before subsequent attempts.
On the practical side, the retention rule softens the cost of a miss. If you pass five tasks and fail one, you repeat only the failed task. That makes a targeted retake plan far more efficient than starting over.
If you fail the written exam, your 30-day gap is your study window. Use it diagnostically: identify whether you lost points in the heavy domains (Grounding & Bonding, Overcurrent Protection, Services, Feeders & Branch Circuits) or scattered them across small domains, and rebuild accordingly. Each retake also carries cost, so see the UT-JE certification cost breakdown for how fees add up.
Eligibility and Fees That Come Before Any Score
Your passing score only matters once you are cleared to sit for the exam. Several gates come first.
Eligibility to Test
The bulletin's eligibility route is either:
- Four-year apprenticeship education of at least 576 classroom hours (or the specified competency equivalent), plus 6,000 licensed-apprentice work hours; or
- 16,000 licensed-apprentice work hours.
First-time candidates must submit Verification of Electrician Experience to Prov, with registration effective January 19, 2026. See our UT-JE requirements guide for the full qualification picture.
Fees and an Unresolved Item
- Written exam: $85.
- DOPL application processing fee: previously listed at $116 in the electrician application revision reviewed earlier.
Two items need honest caveats. First, the Commerce licensing pages and application PDF returned access errors during our latest research pass, so the $116 application fee and the license renewal details are carried forward from earlier review rather than freshly confirmed. Confirm both with DOPL before budgeting.
Second, the practical exam fee is unresolved. The bulletin lists $25 per section but also retains legacy $85 practical-examination wording, with inconsistent language about whether pricing applies to all tasks or one. Neither an $85 total nor a calculated six-section total is reliably established by that conflicting text. Confirm the actual payable charge with Prov before you register.
Building a Plan Around the Score
Rather than a generic schedule, tie your calendar to where the points are. A 75-correct target and a six-task practical suggest this ordering:
Largest written blocks first
- Grounding & Bonding (ten items), then Overcurrent Protection (nine items).
- Tab your 2023 NEC as you go so lookups become automatic.
Calculation-heavy domains
- Current, Voltage, Resistance, Power, and Voltage Drop.
- Services, Feeders & Branch Circuits (eight items) with table-driven problems.
Remaining coverage and the practical
- Conductors & Cables, Raceways & Enclosures, Lighting, Motors & Controllers, Special Occupancies, State Laws & Rules.
- Hands-on rehearsal of all six practical tasks, with conduit bending getting extra reps.
Keep practical rehearsal safe: wire and test circuits de-energized, and have a qualified person energize only when appropriate, mirroring the exam's own sequence. For structured written practice, you can work through questions on our UT-JE practice test site, and our UT-JE training overview covers how formal preparation fits alongside on-the-job hours.
Frequently Asked Questions
You need 75% on the 100-question combined Theory and Code written exam, meaning at least 75 correct answers. The exam is open book, computer-based, and allows 240 minutes.
The bulletin's published standard is the overall 75% passing score. The domains have official item counts, such as ten for Grounding & Bonding, but those are question allocations, not separate pass thresholds.
There is no single percentage. The practical has six tasks within a 110-minute limit, and every task must be passed. Conduit bending uses point deductions; the other tasks are pass/fail. Passed tasks are retained if you need to retest.
Retesting normally requires 30 days. After six failed attempts, the bulletin requires 120 days before subsequent attempts.
No. Only the calculator provided in Prov's test console is authorized. Approved references like the 2023 NEC and Ugly's Electrical References 2023 are permitted, and highlighting and permanent tabs are allowed.
For related planning, see UT-JE exam dates and scheduling and our analysis of whether the UT-JE certification is worth it.